  • CLIENT

    Federici Stirling Batco

  • LOCATION

    Muscat Municipality – Sultanate of Oman

Works are intended to increase the global stability of the hill of Wadi Adai where an electric pylon is located at the top. In fact it was proved that the pylon block had high susceptibility for sliding during excavation works for Wadi Adai Interchange.

The intervention involved two phases:

Phase 1 – Local solution for strengthening foundation. – Micro piling around each of the four foundations of the pylon. 18 micropiles were executed; as support to a concrete slab embracing the top part of the micropiles and the pylon leg.

Phase 2 – Global stability of the Hill – Increasing the stability of the hill by means of 152 micropiles, forming three arcs shape located on the southern side of the hill, micropiles joined at the top by mean of three concrete beams.

For both phases all micropiles were bored and cast in situ and reinforced with a steel pipe over a length of 18 m.

Services provided by Sering International

  • Planning of geotechnical investigations
  • Carrying out structural survey along the top of the hill
  • Critical elaboration of the experimental data from on-site investigations and laboratory tests, to examine the physical-mechanical properties of rock
  • Geotechnical and geo-mechanical characterization of soils and rocks
  • Evaluation of the slope stability and study of failure mechanisms
  • Research, geotechnical terms, the best solutions for increasing the global stability of the hill and strengthening the pylon foundation
  • Detailed and construction design of the remedial works
  • Technical assistance to the Contractor during construction